This has been a slow period for this project. I sprayed the body with undercoat and set it aside. The body isn’t finished, but the remaining work needs to be done after the underframe is fitted. Since then, the project has stuttered along, partly due to non-modelling demands and partly due to waiting three weeks for materials to arrive from suppliers.

The cross-bar is not exactly square to the wagon centre-line because I forgot to check that the two posts were fitted so that the (slightly off-centre) holes for the cross-bar were properly aligned (DOH!)

I began the underfloor with great enthusiasm; first, cutting and test fitting the .010″ styrene sub-floor. Then the chassis rails were made of lengths of .060″ styrene. Because the wagon floor and sub-floor assembly is thicker than on the prototype, the model boards needed to be slightly shallower than scale. Everything was going swimmingly and I was feeling happy with the rate of progress. Pride comes before a fall, as they say.

The time had come to mark the bogie centres and test fit the wagon sitting on the underfloor and a pair of HO-scale bogies with dummy .060″ bolsters temporarily in place – that’s when reality hit hard! The bogies cleared the floor and fitted within the inner side-frames, BUT they could barely turn. My error was so obvious, that I couldn’t believe it. In fact, it’s a compound error. First, the prototype runs on 2′ gauge track (12mm in 1:48 scale). Second, related to the first, the wagon is much narrower than one which would run on 30″ track, so the inner frames severely restrict how much the bogies can swing.
The project went into abeyance at this point while I licked my wounds and thought the issue through, plus I needed to source some 12mm-gauge bogies and other materials. Ultimately, I purchased a pair of Wuiske HOn3.5 QR 5′ archbar bogies with 10.6mm spoked wheels – the best available option (in fact, the only available option). When those and the other materials arrived, the build continued.
I began with the brake gear and fittings; the first of which were the brackets that support the manual brake handles and operating rod. They are made from .015″ styrene. I did consider using metal, but decided in favour of styrene. I glued two ‘blanks’ together so that the finished items would be identical. Next, the brake handles were fettled, also in .015″ styrene. Various other levers were also made with either .015″ or .020″ styrene. The levers and operating rods were linked with yoke-like couplings that I made by gluing .010″ styrene strip to the ends of .020″ styrene rod. A few strokes with a file rounded their corners. Finally, I drilled .015″ holes through the yokes and associated lever end and inserted lengths of .015″ phosphor-bronze wire. The wire was glued and trimmed once the assembly was in place on the wagon.




The pre-assembly work was almost complete. The bolsters were bolstered to their full depth. Then, I test-fitted the entire brake assembly, so that the brake rods could be trimmed and yokes fitted to their outer ends. Those rods attach to fittings on the bolsters.

So, that nearly completed the underfloor work. Final items include brake piping (not shown on the plan), truss rods, handbrake lever locking bars and trimming the manual brake rod. Then, a final check and tidy-up before returning to the body.

So, after sitting untouched for nearly three weeks while waiting for the bogies to arrive, the project has kicked on and the underfloor work largely completed within two days. Once I’ve sorted out the truss rods and the brake piping, I’ll be able to turn my attention to adding the body details. Onward.





























































