Deadlines vs. Estimates
Deadlines vs. Estimates:
The basic difference is this:[...]
- Deadlines come from external sources, for example, “Feature X needs to be ready for the summer trade show”.
- Estimates come from internal sources, for example, “Feature X will take me N weeks to complete”.
If the deadline is shorter than the estimate however, then that’s when the problems start. Here’s a few hints to help ease this situation:
- Hint for managers: Let the person doing the work create the estimate
- Hint for managers: Don’t override an estimate with a deadline
- Hint for developers: Respect for your estimates only flows from accurate estimates
- Hint for developers: Accurate estimates come from tiny tasks
- Hint for developers: Review your estimates after the event
- Hint for marketing: Explain the reason for the deadline