A presentation on Capital and Construction updates was given at the February 2026 Board Study Session. A recording can be watched at the beginning of the video below.
Skyline High Update – February 2026
Academics:
- Punch list and warranty ongoing
Performing Arts Demo:
- Asbestos abatement and utility management
Performing Arts:
- Southeast parking concrete steps completed
- Exterior material installation ongoing
- Relocation of air handler to Mechanical Room
- Concrete floor preparation
- Blackbox Theater progress
- Corridor wall panel installation progress
- Band and Choral Room acoustical fabric wallpanels
- Auditorium wall paneling
- Auditorium soffit and light fixture installation
Cyprus High Update – November 2025
Work on some finishing touches continues at Cyprus High School. Click here for a presentation and photos.
Site Work/Exterior Building:
- Parking lot island landscaping
- Baseball/Softball AV
- Visitor side bleacher gates
Athletics/Pool:
- Weight Room/Cardio AV
- Pool Locker Room/Observation Deck doors
- Gym shade control
Administration/Commons:
- Testing Center projector
- Motors installed on the Serving Area doors
- Digital vinyl wall covering
- Operational Kitchen
- Column extension in Crow’s Nest
Academics/CTE/Social Studies:
- Metal Shop copper piping
- Welding booths
- Electric kilns
Performing Arts:
- Elevator completed
Skyline Progress Photos
Click on the links below to view recent photos of construction progress at Skyline High School. The photos are organized by month in reverse order.
- February 2026
- November 2025
- September 2025
- August 2025
- July 2025
- June 2025
- May 2025
- April 2025
- March 2025

Historic Cost Escalations Delay Start of Projects
Historic increases in construction costs have impacted the original timeline for school rebuilds and remodels. As such, this page will be updated annually to reflect current economic conditions. The most recent estimates are as of November 2025. Reasons for project delays include:
- Annual cost increases since 2016 have been higher than previous trends.
- Increases are related to labor shortages, material costs, tariffs, and supply chain issues.
- Local construction market conditions have out-paced national trends due to population growth.
- Cost increases are anticipated to be near 10% for the next few years.
The Phase 1 timeline is still based on a ‘worst first’ schedule. In addition to these major projects, security upgrades and small scale remodels will continue. Read more about the impacts of cost escalations on school projects.
The anticipated start dates for Phase 1 projects are listed below.
| SCHOOL | PROJECT | ORIGINAL PROJECTED START DATE | PROJECTED START DATE - 2019 | PROJECTED START DATE - 2025 | Status |
|---|---|---|---|---|---|
| Evergreen Jr. High | Remodel | 2018 | 2018 | Completed | |
| Valley Jr. High | Remodel | 2018 | 2018 | Completed | |
| Roosevelt (Olene Walker Elementary) | Rebuild | 2018 | 2019 | Completed | |
| South Kearns | Rebuild | 2018 | 2019 | Completed | |
| Hunter High School | Addition | 2018 | 2019 | Completed | |
| Howard Driggs Elementary | Remodel | 2019 | 2019 | Completed | |
| Rosecrest Elementary | Remodel | 2019 | 2019 | Completed | |
| Cyprus High School | Rebuild | 2020 | 2021 | Completed | |
| Skyline High School | Rebuild | 2020 | 2020 | Under construction | |
| West Kearns Elementary | Rebuild | 2019 | 2027 | 2027 | |
| Calvin Smith Elementary | Remodel | 2021 | 2028 | 2027 | |
| Moss Elementary | Remodel | 2021 | 2028 | 2028 | |
| Plymouth Elementary | Remodel | 2021 | 2028 | 2028 | |
| Taylorsville High School | Addition | 2022 | 2028 | 2026 | |
| Arcadia | Rebuild | 2022 | 2029 | 2029 | |
| Hillsdale Elementary | Remodel | 2023 | 2029 | 2029 | |
| Kennedy Jr. High | Remodel | 2023 | 2029 | 2029 | |
| Orchard Elementary | Rebuild | 2023 | 2031 | 2031 | Closed - 2025 |
| Magna Elementary | Remodel | 2024 | 2032 | 2032 | |
| Valley Crest Elementary (Now Dos Mundos Academy) | Remodel | 2024 | 2032 | 2032 | |
| Kearns Jr. High | Rebuild | 2024 | 2033 | 2030 | |
| Sandburg Elementary | Rebuild | 2025 | 2033 | 2033 | Closed - 2019 |
| Lincoln Elementary | Remodel | 2025 | 2033 | 2033 | |
| Pioneer Elementary | Remodel | 2025 | 2033 | 2033 | |
| Academy Park Elementary | Rebuild | 2024 | 2034 | 2031 | |
| Crestview Elementary | Remodel | 2026 | 2034 | 2033 | |
| Eastwood Elementary | Rebuild | 2026 | 2035 | 2032 | |
| Cottonwood Elementary | Remodel | 2027 | 2035 | 2033 | |
| Spring Lane Elementary | Rebuild | 2027 | 2036 | 2036 | Closed - 2023 |
| Valley Jr. High | Rebuild | 2028 | 2036 | 2034 | |
| Evergreen Jr. High | Rebuild | 2028 | 2037 | 2035 | |
| Oakridge Elementary | Rebuild | 2028 | 2037 | 2033 |
The New Cyprus High is Open!
Select Cyprus High Construction Tour – June 2025
Cyprus High Construction Tour – March 2025
Skyline High School Update
What is the Project Status?
Students have been enjoying the fully-completed academics building and athletic facilities this school year (2024/2025).
The auditorium and remaining classrooms will be completed in time for the 2026/2027 school year. Some minor site, parking lot, and landscaping work will continue into the 2026/2027 school year.