Active Incident

Updated a few seconds ago

Incident Status

Partial Service Disruption

Components

CoreWeave Infrastructure, CoreWeave Object Storage, CoreWeave Services, CoreWeave Inference

Locations

US-EAST-15



October 22, 2026 9:32PM UTC
IDENTIFIED

Hello, We are actively investigating a facility power event in US-EAST-15A following the loss of both utility power feeds at the site. Customers in this region may experience compute unavailability, job interruptions, , Inference disruptions and degraded or unavailable Object Storage. Our engineering and facilities teams are actively working to restore stable power and cooling. Impact may continue or widen until site conditions stabilize. If you are impacted or have questions, please contact support@coreweave.com. We apologize for the disruption and thank you for your patience. Thank you, CoreWeave Support

October 23, 2026 12:05AM UTC
MONITORING

The disruption has been traced to a tripped main feed from the local utility provider, who is actively troubleshooting on site. The facility is running on backup generator power, cooling has been restored, and room temperatures are returning to normal. When utility power gets restored, we will begin bringing systems back online in stages, prioritizing restoring customer capacity. A subset of racks sustained a cooling related hardware issue during the event and require servicing before they can be powered back on; we currently estimate these will be restored by Friday morning. We expect more information on the utility power timeline within the next hour and will post more updates

October 23, 2026 3:06AM UTC
MONITORING

Power has been restored and node recovery is underway. Nodes are being brought back online in phases, starting with air cooled systems; B200 (liquid cooled) nodes will follow once that first phase completes. We expect full recovery by Morning time due to the subset of racks which sustained a cooling issue during the event and require servicing before they can be powered back on. We'll share more updates as more nodes return to service.

October 23, 2026 9:05PM UTC
MONITORING

Most capacity in US-EAST-15A has been restored following the facility power event. Power is stable, and we are not expecting a repeat of the utility disruption. A subset of racks still requires follow-on facility work (including coolant servicing) before they can be safely returned to service. Recovered capacity remains available for use while that work continues. We will keep this incident in Monitoring until remaining facility recovery is complete, and will post another update when that work wraps up or if the situation changes. Thank you, CoreWeave Support

October 25, 2026 12:43AM UTC
INVESTIGATING

We are investigating a renewed cooling disruption at the US-EAST-15A facility, with additional racks shutting down and customer impact observed. Customers in this region may experience compute unavailability, job interruptions, and inference disruptions. Our engineering and facilities teams are working with the facility provider to determine the cause and restore stable cooling. Impact may continue or widen until site conditions stabilize. If you are impacted or have questions, please contact support@coreweave.com. We apologize for the renewed disruption and thank you for your patience. Thank you, CoreWeave Support

October 25, 2026 2:06AM UTC
INVESTIGATING

Our facility provider has confirmed a renewed loss of utility power at US-EAST-15A, and the site is currently running on backup generators. The utility provider is investigating the power loss, while the facility's cooling specialists are on site investigating the cooling disruption. We apologize for the continued disruption and thank you for your patience. If you are impacted or need assistance, please contact support@coreweave.com. Thank you, CoreWeave Support

October 26, 2026 4:27AM UTC
MONITORING

Power has been restored at US-EAST-15A, and we're working to stabilize the site. Most affected nodes are back in service, and we're bringing the remaining nodes back online. We'll continue to monitor the site and share updates as recovery progresses.

CoreWeave Cloud




Operational

CoreWeave Infrastructure




Partial Service Disruption

CoreWeave Premium Shared Filesystem Volumes




Operational

CoreWeave Object Storage




Partial Service Disruption

CoreWeave Services




Partial Service Disruption

CoreWeave Logging




Operational

CoreWeave Inference




Partial Service Disruption

CoreWeave Shared Filesystem Volumes




Operational

CoreWeave Block Storage Volumes




Operational

Coreweave Network




Operational

CoreWeave Bare Metal




Operational

CoreWeave Networking




Operational

CoreWeave Cloud Console




Operational

3

Upcoming Maintenances

5

Incidents Last 30 Days

12

Maintenances Last 30 Days

External Services

Scheduled Maintenance

Schedule

November 2, 2026 11:30PM - November 5, 2026 1:00AM UTC

Components

CoreWeave Infrastructure

Locations

CA-EAST-01

Description

Details: CoreWeave will perform scheduled power infrastructure maintenance in CA-East-01A between 2 November 2026 at 11:30 UTC and 5 November 2026 at 01:00 UTC. Work will occur in separate maintenance periods within this overall window. Location: CA-East-01A Scope: Install permanent power quality meters and branch circuit monitoring, and complete associated corrective work on Optistax power distribution unit 11E and 11F. Each unit will be isolated individually for up to two days, including overnight isolation where required. Power will be restored and equipment validated before work begins on the next unit. Impact: No customer service interruption or disruption to CDU operation is expected. Equipment supplied by the unit under maintenance will temporarily operate on its remaining redundant power sources. Power redundancy will be reduced during each isolation period and restored after that unit’s work is complete. We will actively monitor systems throughout the maintenance. If you have questions or require assistance, please contact our support team at support@coreweave.com. This activity is deemed Planned Maintenance under the CoreWeave Terms of Service Maintenance Policy (docs.coreweave.com/policies/terms-of-service/maintenance-policy).

Schedule

November 9, 2026 11:30PM - November 12, 2026 1:00AM UTC

Components

CoreWeave Infrastructure

Locations

CA-EAST-01

Description

Details: CoreWeave will perform scheduled power infrastructure maintenance in CA-East-01A between 9 November 2026 at 11:30 UTC and 12 November 2026 at 01:00 UTC. Work will occur in separate maintenance periods within this overall window. Location: CA-East-01A Scope: Install permanent power quality meters and branch circuit monitoring, and complete associated corrective work on Optistax power distribution unit 11G and 11H. Each unit will be isolated individually for up to two days, including overnight isolation where required. Power will be restored and equipment validated before work begins on the next unit. Impact: No customer service interruption or disruption to CDU operation is expected. Equipment supplied by the unit under maintenance will temporarily operate on its remaining redundant power sources. Power redundancy will be reduced during each isolation period and restored after that unit’s work is complete. We will actively monitor systems throughout the maintenance. If you have questions or require assistance, please contact our support team at support@coreweave.com. This activity is deemed Planned Maintenance under the CoreWeave Terms of Service Maintenance Policy (docs.coreweave.com/policies/terms-of-service/maintenance-policy).

Schedule

November 16, 2026 11:30PM - November 19, 2026 1:00AM UTC

Components

CoreWeave Infrastructure

Locations

CA-EAST-01

Description

Details: CoreWeave will perform scheduled power infrastructure maintenance in CA-East-01A between 16 November 2026 at 11:30 UTC and 19 November 2026 at 01:00 UTC. Work will occur in separate maintenance periods within this overall window. Location: CA-East-01A Scope: Install permanent power quality meters and branch circuit monitoring, and complete associated corrective work on Optistax power distribution unit 11i and 11J. Each unit will be isolated individually for up to two days, including overnight isolation where required. Power will be restored and equipment validated before work begins on the next unit. Impact: No customer service interruption or disruption to CDU operation is expected. Equipment supplied by the unit under maintenance will temporarily operate on its remaining redundant power sources. Power redundancy will be reduced during each isolation period and restored after that unit’s work is complete. We will actively monitor systems throughout the maintenance. If you have questions or require assistance, please contact our support team at support@coreweave.com. This activity is deemed Planned Maintenance under the CoreWeave Terms of Service Maintenance Policy (docs.coreweave.com/policies/terms-of-service/maintenance-policy).

History

No incidents in the last day